They are working "extended hours" on the piping system of the Guiteras, which has not yet started

Maintenance of the GuiterasPhoto © Facebook / CTE Guiteras

The Antonio Guiteras Thermal Power Plant, the largest electricity generation facility in Cuba, remains out of service this Sunday as welding crews work tirelessly to restore the piping system that would allow for its reactivation.

The official central account on Facebook reported that work is being carried out "with extended hours" to restore the raw water input piping system to the tanks, described as "a matter of vital importance for the startup and commissioning of the unit."

The plant went offline from the National Electroenergy System on Wednesday, November 11 — its 28th outage so far in 2026 — while generating approximately 180 MW, due to a leak in the boiler economizer. A subsequent inspection revealed punctures in the economizer, the high-temperature reheater, and the nurse area.

The engineer Elmer García Romero, technical deputy director of the block, confirmed to Radio 26 that "along with the repair of the malfunction in the economizer, the most deteriorated element in the plant, around 180 corrective tasks are being undertaken, with the support of the Central Repair Unit and brigades from the maintenance company for power plants in the west."

The welding brigades from ESTEC and the power plant itself have been working continuously, including night shifts, as can be seen in the images published by the facility, where dozens of workers with protective equipment are working under construction lights in the early morning hours.

The matancero journalist José Miguel Solís, specializing in monitoring the installation, predicted on Friday, November 13 that the plant could start up in the early hours of Monday, November 16. However, by the close of this Sunday, work on the raw water piping system continued, and the unit remained classified as out of service due to a malfunction.

The situation worsens an electricity crisis that is already at critical levels. This Sunday, the Unión Eléctrica forecasted only 970 MW available against a demand of 2,800 MW, resulting in a deficit of 1,830 MW and blackouts of up to 20 hours a day in many provinces.

The shutdown of the Guiteras is joined by other major power plants that are halted: the CTE Ernesto Guevara lost its last active unit on Friday, November 13, leaving its three blocks—with a combined capacity of 295 MW—completely inoperative, while the CTE Felton in Holguín has gone weeks without generating a single megawatt.

La Guiteras has accumulated nearly 38 years of operation and approximately 16 years without a complete capital repair, which explains the frequency of its breakdowns. The General Director of the Electric Union, Rubén Campos Olmos, estimated in June 2026 that a comprehensive repair would require intervening on more than 500 tubes, executing between 1,000 and 1,200 welding seams, and keeping the unit offline for about six months, a timeframe that the SEN cannot accommodate without sufficient backup generation.

While the welders continue their nighttime work, Monday, November 16, remains the scheduled date for Guiteras to enter the system, although the plant itself has not confirmed a specific start time.