The United States Department of Defense committed more than 81 million dollars to relocate and retain migrants at the Guantanamo Naval Base in Cuba, although only 849 individuals have passed through that facility since the operation began, according to a report from the Pentagon's Inspector General published on November 25.
The figure stands in stark contrast to the promise made by President Donald Trump, who announced in January 2025 that Guantánamo would host up to 30,000 migrants.
"We have 30,000 beds in Guantánamo Bay to detain the worst illegal foreign criminals who threaten the American people. This will immediately double our capacity," he stated.
The reality documented by the audit was radically different: the actual maximum capacity of the detention center never exceeded 399 people, and at the end of the audited period, on September 3, 2026, only eight migrants remained at the base.
The report, covering the period from July to September 2026, details that the majority of the spending fell on the Army, with approximately $60.6 million committed, followed by the Navy with $20.8 million.
In just the last quarter, the cost of accommodating migrants rose to 2.53 million dollars, although the contracts also covered personnel, air transportation, and other operations.
During that same period, about 350 military personnel remained deployed in Guantanamo in support of the Department of Homeland Security, despite the fact that the number of detainees was minimal.
Out of a total of 849 migrants processed since the beginning of the operation, 632 were repatriated to their home countries, 209 were relocated to other centers within the United States, and eight remained at the base as of September.
The average length of stay was seven days in the last quarter, although one individual managed to stay for 102 days, partly due to their home country's refusal to accept their repatriation and limitations in flight scheduling.
The planning deficiencies were pointed out from the outset. A source with direct knowledge of the situation warned in January 2025: "There should have been a greater degree of planning before execution. Now execution has begun, and everyone is trying to improvise on the go."
This report is not the first to question the operation. In October 2026, Democratic Senate staff published their own report which found 445 employees assigned to the mission and no migrants detained during a visit made in August.
That document estimated a cost of approximately 118,000 dollars for each migrant who went through the facility.
The Office of Government Accountability also documented that the Pentagon erected tent facilities capable of housing 5,000 people, which were dismantled without having housed a single detainee, at a cost of 2.85 million dollars.
Despite the negative balance, the Trump administration is considering expanding the network of detention centers to up to 14 locations, including a new facility in Guantanamo, with a potential budget of up to 10 billion dollars.