La Guiteras returns to the SEN, but the UNE forecasts outages of up to 1,760 MW

Antonio Guiteras Thermoelectric Power PlantPhoto © Facebook/Cte Antonio Guiteras

The Antonio Guiteras Thermoelectric Power Plant, the largest power generation unit in Cuba, synchronized with the National Electric System this Monday after five days of emergency repairs, but its reactivation is not enough to alleviate the electricity crisis affecting the country.

The Matanzas journalist José Miguel Solís, who is closely following the installation, confirmed that the plant "stabilizes parameters and increases load" after synchronization. The official account of the plant on Facebook also announced it with the message "The Antonio Guiteras thermoelectric plant synchronized with the National Electrical System."

The plant had gone offline on Wednesday, November 11 —its 28th outage so far in 2026— due to a leak in the economizer of the boiler, when it was generating approximately 180 MW.

The subsequent inspection revealed multiple damages: punctures in the economizer, in the high-temperature reheater, and in the area of the feedwater heater. The technical deputy director of the block, Elmer García Romero, confirmed to Radio 26 that "around 180 corrective tasks were being carried out, with the support of the Central Repair Unit and brigades from the maintenance company for electrical plants in the west."

On Sunday, welding brigades from ESTEC and the central plant itself were working extended hours on restoring the raw water intake pipe system, which has been described as "a task of vital importance for the start-up." The sync on Monday met the expectations that Solís had outlined on Friday the 13th.

However, the return of the Guiteras does not resolve the structural deficit of the system. According to the report from Unión Eléctrica (UNE) for this Monday, at six in the morning, the availability of the SEN was only 870 MW compared to a demand of 2,070 MW, with 1,186 MW already affected at that time.

For the half-hour period, a reduction of 1,400 MW was anticipated. The commissioning of Guiteras with 180 MW and the completion of unit 6 of Nuevitas with an additional 20 MW would raise the availability to 1,070 MW, a figure significantly lower than the expected peak demand of 2,800 MW.

"With this forecast, it is estimated that during peak demand hours, there will be a availability of 1,070 MW with a maximum demand of 2,800 MW, resulting in a deficit of 1,730 MW. Therefore, if the expected conditions are maintained, an impact of 1,760 MW is predicted during this period," warned the UNE.

Sunday was one of the worst days of the month: the service was interrupted for 24 hours, including the early morning, and the peak impact reached 1,874 MW at 7:00 PM.

With the Guiteras now operational, unit 8 of the Mariel Thermal Power Plant, unit 1 of the Santa Cruz Thermal Power Plant, and unit 2 of the Felton Thermal Power Plant remain out of service. Currently under maintenance are unit 3 of Santa Cruz, unit 5 of Nuevitas, unit 1 of Felton, and unit 5 of Renté. The limitations in thermal generation amount to 281 MW.

The crisis worsened recently with the complete shutdown of the CTE Ernesto Guevara (Santa Cruz del Norte), whose three units —295 MW of combined capacity— were entirely out of service on Friday the 13th, and with both units of the CTE Felton inoperative since November 10th.

La Guiteras has accumulated nearly 38 years of operation and approximately 16 years without a complete overhaul. The general director of the UNE, Rubén Campos Olmos, estimated in June that a comprehensive intervention would require keeping the plant out of the system for about 180 days, a timeframe that the SEN cannot accommodate. The plant's director, Román Pérez Castañeda, summed it up clearly: "The situation in the country still does not allow it."